Content provided by Ingrid Velasquez-Woodley and Fohlio Inc.. All podcast content including episodes, graphics, and podcast descriptions are uploaded and provided directly by Ingrid Velasquez-Woodley and Fohlio Inc. or their podcast platform partner. If you believe someone is using your copyrighted work without your permission, you can follow the process outlined here https://player.fm/legal.
Player FM - Podcast App
Go offline with the Player FM app!

Protect Your Bottomline: Differing Site Conditions and Change Orders (Crash Course: Contract Law with Wally Zimolong)

1:10:57
 
Share
 

Manage episode 280857976 series 2845040
Content provided by Ingrid Velasquez-Woodley and Fohlio Inc.. All podcast content including episodes, graphics, and podcast descriptions are uploaded and provided directly by Ingrid Velasquez-Woodley and Fohlio Inc. or their podcast platform partner. If you believe someone is using your copyrighted work without your permission, you can follow the process outlined here https://podcastplayer.com/legal.

Differing site conditions is what happens when you’re working on a project and you encounter conditions in the field that differ from the drawings that you were provided, what was represented to you, and what you could have reasonably anticipated.

Unfortunately, no matter how well any project is thought out and arranged, it’s rarely the case that everything goes exactly according to plan. This is why you’re going to need agreements for how to deal with those unexpected situations and the changes that follow.

Of course, both parties have a lot at stake and this is where change clauses can become a really fertile ground for dispute — not just legally but emotionally, as well.

It’s important that those change orders get paid, from the contractor’s perspective, because it could be the difference between a profitable or unprofitable job.

On the other hand, there’s nothing a project owner hates more than having a contractor come to him and say, “I couldn’t have anticipated encountering these conditions and so it’s going to cost you 25% more to complete your project.”

So how do you avoid disputes? This is where clauses for differing site conditions and change orders come into play.

  continue reading

16 episodes

Artwork
iconShare
 
Manage episode 280857976 series 2845040
Content provided by Ingrid Velasquez-Woodley and Fohlio Inc.. All podcast content including episodes, graphics, and podcast descriptions are uploaded and provided directly by Ingrid Velasquez-Woodley and Fohlio Inc. or their podcast platform partner. If you believe someone is using your copyrighted work without your permission, you can follow the process outlined here https://podcastplayer.com/legal.

Differing site conditions is what happens when you’re working on a project and you encounter conditions in the field that differ from the drawings that you were provided, what was represented to you, and what you could have reasonably anticipated.

Unfortunately, no matter how well any project is thought out and arranged, it’s rarely the case that everything goes exactly according to plan. This is why you’re going to need agreements for how to deal with those unexpected situations and the changes that follow.

Of course, both parties have a lot at stake and this is where change clauses can become a really fertile ground for dispute — not just legally but emotionally, as well.

It’s important that those change orders get paid, from the contractor’s perspective, because it could be the difference between a profitable or unprofitable job.

On the other hand, there’s nothing a project owner hates more than having a contractor come to him and say, “I couldn’t have anticipated encountering these conditions and so it’s going to cost you 25% more to complete your project.”

So how do you avoid disputes? This is where clauses for differing site conditions and change orders come into play.

  continue reading

16 episodes

All episodes

×
 
Loading …

Welcome to Player FM!

Player FM is scanning the web for high-quality podcasts for you to enjoy right now. It's the best podcast app and works on Android, iPhone, and the web. Signup to sync subscriptions across devices.

 

Copyright 2025 | Privacy Policy | Terms of Service | | Copyright
Listen to this show while you explore
Play