Go offline with the Player FM app!
Inside MARA's Flagship Granbury Site!
Manage episode 519324050 series 3570269
We tour MARA’s Granbury flagship to show how a 260 MW Bitcoin mine runs quietly beside a natural gas plant and why 67% of rigs now sit in immersion. We break down modular build speed, behind‑the‑meter power, vertical integration, and load balancing with HPC.
• 260 MW flagship site with 12.2 EH contribution
• Immersion cooling adoption at 67% of active machines
• Modular container strategy for rapid energization
• Acoustic wall and gravel plan for noise and dust control
• On‑site repair workflow and visual monitoring software
• 20‑second curtailment capability for grid support
• Behind‑the‑meter access to natural gas power
• Vertical integration shift to ~70% owned facilities
• Mining and HPC complement for load balancing
• Local jobs and school robotics sponsorship
Hit the like button. Feel free to subscribe. Let us know if you have any questions for the team at Mara and what you thought of today's video.
Anthonys Info:
Website:
https://www.powermininganalysis.com
X:
https://twitter.com/cazenove_uk
Patreon:
https://www.patreon.com/Cazenove_UK
Bryce's Info:
X:
Patreon:
https://www.patreon.com/McNallieMoney
Merch:
https://shop.mcnalliemoney.com/
Website:
Business Inquiries:
Email - [email protected]
Chapters
1. Welcome And Tour Setup (00:00:00)
2. Finding The Site And Security (00:01:50)
3. Orientation And On‑Site Repair Ops (00:03:35)
4. Granbury Scale And Immersion Push (00:05:55)
5. Modular Containers And Noise Wall (00:09:35)
6. Air‑Cooled Design And Filtration (00:13:30)
7. Speed To Energize And Flexibility (00:17:30)
445 episodes
Manage episode 519324050 series 3570269
We tour MARA’s Granbury flagship to show how a 260 MW Bitcoin mine runs quietly beside a natural gas plant and why 67% of rigs now sit in immersion. We break down modular build speed, behind‑the‑meter power, vertical integration, and load balancing with HPC.
• 260 MW flagship site with 12.2 EH contribution
• Immersion cooling adoption at 67% of active machines
• Modular container strategy for rapid energization
• Acoustic wall and gravel plan for noise and dust control
• On‑site repair workflow and visual monitoring software
• 20‑second curtailment capability for grid support
• Behind‑the‑meter access to natural gas power
• Vertical integration shift to ~70% owned facilities
• Mining and HPC complement for load balancing
• Local jobs and school robotics sponsorship
Hit the like button. Feel free to subscribe. Let us know if you have any questions for the team at Mara and what you thought of today's video.
Anthonys Info:
Website:
https://www.powermininganalysis.com
X:
https://twitter.com/cazenove_uk
Patreon:
https://www.patreon.com/Cazenove_UK
Bryce's Info:
X:
Patreon:
https://www.patreon.com/McNallieMoney
Merch:
https://shop.mcnalliemoney.com/
Website:
Business Inquiries:
Email - [email protected]
Chapters
1. Welcome And Tour Setup (00:00:00)
2. Finding The Site And Security (00:01:50)
3. Orientation And On‑Site Repair Ops (00:03:35)
4. Granbury Scale And Immersion Push (00:05:55)
5. Modular Containers And Noise Wall (00:09:35)
6. Air‑Cooled Design And Filtration (00:13:30)
7. Speed To Energize And Flexibility (00:17:30)
445 episodes